JKPCC incurs loss of Rs
1.64 cr
BILAL HUSSAIN
In
yet another instance of growing nepotism in the state run corporations that
results in colossal loss of tens of crores rupees, the latest audit report by the
Comptroller and Auditor General of India, highlights undue favour to contractor
in the Jammu and Kashmir Projects Construction Corporation Limited in Jammu and Kashmir (JKPCC).
According to the Comptroller and Auditor General (CAG) report
the allotment of work by the Jammu and Kashmir Projects Construction
Corporation Limited, a government owned company incorporated in 1965, without
inviting tenders and payment of unsecured interest free mobilization advance to
the contractor resulted in undue favour to contractor and interest loss of Rs
1.64 crore.
The Jammu and Kashmir Projects Construction Corporation
Limited (JKPCC) signed a Memorandum of Understanding (MOU) with J&K Power
Development Corporation (JKPDC) both State Public Sector Undertakings in December,
2006 for construction of Motorable R.C.C Bridge at Ganpat, Doda at a cost of Rs
29.95 crore, which included 15 per cent supervision charges (Company’s share)
of Rs 4.49 crore, for completion by February 2009.
An amount of Rs 5.99 crore was received in December
2006/March 2007 by the JKPCC from the JKPDC as Mobilization Advance against a
Bank Guarantee for the full amount. The JKPCC allotted the work to a
sub-contractor - M/S A.K. Constructions, Jammu in February 2007 at the cost of Rs
25.46 crore for completion within 25 months (by February 2009). The work,
however, had not been completed as on June 2011, the report reveals.
The audit scrutiny during February 2011 revealed that the JKPCC, while sub-contracting the work, instead of following a transparent
and competitive tendering process, had allotted work to the sub-contractor on
the recommendation in January 2007 of a committee set up by the JKPCC which
had opined that the said contractor had the capacity to undertake such works
and had, in the past, already executed some of the bridge projects with the JKPCC.
The scrutiny of records, however, revealed that though the
committee had recommended allotment of work in January 2007, as per records the
work had already been started by the contractor in November 2006, rendering the
process meaningless. The JKPCC stated in September 2011 that the work had been
allotted to the firm by an MOU between the JKPCC and the sub-contractor.
The reply is not tenable as mere entering into an MOU does
not absolve the JKPCC of the responsibility of following prescribed procedure
laid down in the State Financial Code as well as the guidelines of the Central
Vigilance Commission (CVC) with regard to allotment of contracts, which provide
for transparent tendering process, the report highlights.
The CVC guidelines in October 1997/June 2004/April 2007
prohibit payment of unsecured and interest free mobilization advance. The
guidelines provided that decision to provide such advance should rest at the
level of Board of Directors (with concurrence of Finance) in the organization.
The guidelines further provide that the advance should be released in stages
depending upon the progress of the work, there should be a security by way of
Bank guarantee of an equal amount, a fixed re-payment scheduled and provision
of an interest element in the event of failure to repay.
According to the report in violation of the prescribed guidelines,
it was seen that the sub-contractor was paid an interest free mobilization
advance of Rs 5.09 crore, Rs 1.20 crore in February 2007 and Rs 3.89 crore in
March 2007, immediately on start of the
work. However, no safeguards to secure the advance by way of a bank guarantee
of equivalent amount were insisted upon even though the JKPCC had itself taken
the mobilization advance from the JKPDC against a Bank Guarantee.
The audit noticed that out of total value of work done of Rs
13.06 crore ending June 2011, the contractor had submitted bills to the tune of
Rs 3.80 crore in March 2008 and no other claim had been preferred since then.
An amount of Rs 1.50 crore only out of the mobilization advance had been
adjusted in March 2008 and the balance amount remained unadjusted as of June
2011. The payment of unsecured and interest free mobilization advance paid in
violation of the instructions of the CVC, thus, resulted in interest loss of Rs
1.64 crore— calculated at the rates (9.5 per cent, 10.75 per cent and 11.25 per
cent) charged by Jammu and Kashmir Bank on state government’s overdraft from
time to time— for the period from March 2007 to March 2011 besides, extension
of undue favour to the contractor.
The management in August 2011 stated that the advance had
been given as per the agreement with the contractor. The reply does not justify
payment of advance in violation of guidelines thereby, extending undue benefit
to the contractor, CAG report mentions.
The matter was taken up with the government in July 2011;
the reply was awaited till October 2011, the report said.
The audit report suggests that the JKPCC should take
immediate steps for recovery of the advance and henceforth ensure compliance
with the guidelines/rules in the matters of allotment of contracts and
mobilization advance.
1 comment:
Marvelous…..
puneonnet.com
Post a Comment